Water Projects: | |||||||||||||||||
City Pressure Zone Upgrades | |||||||||||||||||
Cost Estimate: |
|||||||||||||||||
$1 million per year | |||||||||||||||||
Stage of Development: |
|||||||||||||||||
We will be working in conjuction with the Sewer I&I project team as they have a project in the same area. The project will be bid in December 2004. | |||||||||||||||||
Description: | |||||||||||||||||
The year 2005 will mark the beginning of a multi-phase project to upgrade the waterlines in the city pressure zone. The first phase will consist of the areas around Wellmont Hospital including Sewanee, Ravine, etc.
|
|||||||||||||||||