Netherland Inn Bridge Closure
Path Forward ?
make repairs ?
pursue realignment ?
No
pursue realignment ?
Yes
3 case scenarios
3 case scenarios
Criteria:
traffic / community impacts,  financial, sewer, ROW
In order to facilitate the decision making process, Public Works staff analyzed the probable impacts of the six scenarios that would result from answering yes or no to making repairs and pursuing realignment.  The criteria for evaluation included the traffic / community impacts of the closed bridge, overall financial impacts, sewer construction (cost and feasibility), and right-of-way requirements for each scenario.