Bridge Presentation February 17, 2003
1.  Update on Netherland Inn Bridge Replacement
    Pending bridge design issues
Utilities restrictions on new bridge
Rotherwood Drive impacts
On February 17, 2003 Public Works staff provided a bridge presentation to the Board of Mayor and Alderman (BMA).  The first part of the presentation was an update on the status of the Netherland Inn bridge replacement project while the second part provided an overview of the condition of all of Kingsport’s bridges.

This Powerpoint presentation was adapted from the original BMA presentation and only includes the slides related to the update of the Netherland Inn bridge project.  The comprehensive bridge report is available on-line at kingsportpublicworks.com under “Reports and Presentations”.

The two issues highlighted in this Netherland Inn bridge presentation include a discussion of the possible bridge construction impacts on Rotherwood Drive and TDOT utility restrictions on the new bridge.