Next Steps
Netherland Inn Bridge
Continue to re-work final design   No action required         
1.  Rotherwood Drive Impacts
Status                    Board Action
2.  Utilities Restrictions
Tear down bridge & build lift station                  Board direction
       or
Keep bridge for utilities & pedestrians
Status                            Board Action
In summary, Public Works staff will continue to work with the City’s bridge engineering firm over the next couple of months to re-design the new Netherland Inn bridge so that the roadway alignment problems can be resolved without impacting the intersection of Rotherwood Drive and Netherland Inn Road; and based on the direction of the BMA, staff will formally convey the City’s request to TDOT to keep the old bridge in place for use by pedestrians and bicyclists and for City utilities.